Since May, Aurora Fellow, Martin Rubino, has been in Nzara, South Sudan working on increasing capacity at St. Theresa Hospital. In a previous update, Martin shared building plans, photos, and initial thoughts on the work so far. In this piece, Martin shares some of the obstacles he has faced so far. Despite unpredictable setbacks, building progress is continuing steadily.


Update 21 to 27 May, 2018

The good progress made last week and the beginning of this week was somewhat dampened by one of the realities of working in South Sudan – the precarious nature of logistics.  

Cement purchased in Uganda is stockpiled at the contractor’s store in Yambio, about an hour from the project site in Nzara. From there, the bags of cement are transported as needed by truckload. At the end of the day on Wednesday, the remaining bags of cement in Nzara were used up mixing mortar and concrete.

The truck scheduled that day never arrived. On Thursday, again no truck. Because of the recent suspension of the only cellular network in the area, the only way to communicate with Yambio is to send someone to town. In this manner, a rather hazy message was relayed the following day simply stating that there were mechanical issues with the truck. Work continued with backfilling, compacting, and tying rebar, but the question of cement lingered unresolved.

Then, as is often the case here, the clouds lifted just as quickly as they came in, without much explanation and leaving us no less perplexed than before. On Saturday afternoon, a truck with cement arrived, promising the continuation of work next week.

Ups and downs are accepted in stride here. The people know how to continue moving forward even when plans do not fall as neatly into place as we would like.

Overview:

Completion of the foundations was delayed due to lack of cement (unable to transport cement from Yambio to Nzara because of mechanical issues with the truck). While waiting on cement, backfilling, quarrying aggregate, and tying and setting rebar for columns continued. Deliveries of murram soil came in via truckload.

Site Activities

Construction team hard at work at St. Theresa's Hospital in South Sudan

Maternity Ward: Foundations for Safe Delivery

Foundations for the maternity ward were completed last week. Backfill with murram soil was completed this week and mechanical compaction is underway

Foundations for the Maternity Ward were completed last week. Backfill with murram soil was completed this week and mechanical compaction is underway.

Surgical Ward

Constrution of the surgical ward foundation is nearly compelete, minus four columns that need to be filled with cement.

Construction of the Surgical Ward foundations are nearly complete, minus four columns that need to be filled with cement. Backfill with murram soil is underway.

Operating Theater

Completion of the back veranda foundation and columns was delayed due to lack of cement. A stone base was laid to support partion walls of the bathrooms and lockers. Backfill of murram soil is in progressCompletion of the back veranda foundation and columns was delayed due to lack of cement. A stone base was laid to support partition walls of the bathrooms and lockers. Backfill of murram soil is in progress.

Construction Timeline

Construction timeline update

Construction Quick Terms

  • Backfill – Backfilling is a process of refilling the excavated foundation with soil once finished. There are several techniques for backfilling that require knowledge of soil conditions to ensure the foundation is properly protected.
  • Compacting – Soil compaction is an important part of soil construction for foundations. Compaction removes pockets of water and air in the soil, increasing the stability of the soil base while also reducing its tendency to swell from water absorption.
  • Quarrying – A process of extracting rock, sand, gravel, and other minerals for construction use. These materials are commonly referred to as aggregates and can be used to make concrete.
  • Rebar – Rebar is used to strengthen foundations, walls, and other structures that require reinforced concrete.  Tying appropriate knots is crucial to securing rebar and keeping it in place.

Inspired by Martin? Become a volunteer.

Stay up to date, sign up to receive our monthly volunteer newsletter filled with amazing stories about our international volunteers.

Sign up to receive our volunteer newsletter!